2021-11-01

Set dates for upcoming projects

Define target dates for the Subscriber Search Service and Analytics View Service

Service Estimated Effort (days) * 1.5 developers
Subscriber Search 18 12.
Analytics View 19.5 13.
37.5 25.

Assuming we start next sprint ([2021-11-15 Mon]) I expect both projects to be done by [2021-12-24 Fri] - [2022-01-14 Fri] (adding an additional week to account for holiday time). Assuming they are worked sequentially, I expect the first to be completed by [2021-12-03 Fri] - [2021-12-10 Fri]. In these estimates I'm assuming approximately three to four weeks of effort each.

Plan for analytics search testing

Postgres upgrades are planned for the analytics search database. The database is expected to be maintained behind the anasearch.service.staging.consul hostname, which the Control Panel is already configured to be using.

Planning future backend work

Meeting with Scott and Eric.

Number clicked column to account backup 4h
CSLead Tickets EOW
Tagbox upgrades EOW
Remove outbound tag sanitization EOW
Analytics search testing ???
OpenAPI newline pattern validation Tomorrow
Start on Search Service Next week