Set dates for upcoming projects
Define target dates for the Subscriber Search Service and Analytics View Service
Service | Estimated Effort (days) | * 1.5 developers |
---|---|---|
Subscriber Search | 18 | 12. |
Analytics View | 19.5 | 13. |
37.5 | 25. |
Assuming we start next sprint ([2021-11-15 Mon]) I expect both projects to be done by [2021-12-24 Fri] - [2022-01-14 Fri] (adding an additional week to account for holiday time). Assuming they are worked sequentially, I expect the first to be completed by [2021-12-03 Fri] - [2021-12-10 Fri]. In these estimates I'm assuming approximately three to four weeks of effort each.
Plan for analytics search testing
Postgres upgrades are planned for the analytics search database. The database is
expected to be maintained behind the anasearch.service.staging.consul
hostname, which the Control Panel is already configured to be using.
Planning future backend work
Meeting with Scott and Eric.
Number clicked column to account backup | 4h |
CSLead Tickets | EOW |
Tagbox upgrades | EOW |
Remove outbound tag sanitization | EOW |
Analytics search testing | ??? |
OpenAPI newline pattern validation | Tomorrow |
Start on Search Service | Next week |